2026 Total Planned Shipment 8,630,160
Shipped Year to Date 5,725,968
Remaining to be Shipped 2,904,192

Shipment Information

Shipment Planned Shipment Date Planned MDA Date POS (Bottles) # of Treatments Shipment Date Arrival Date Mode
Mali #6 Q2 2026 2026-04-08 2026-06-01 500,016 2,000,064 2026-04-23 ocean
Mali #7A Q2 2026 2026-04-15 2026-06-01 558,120 2,232,480 2026-04-04 2026-04-17 air
Mali #7B Q2 2026 2026-04-15 2026-06-01 99,180 396,720 2026-04-04 2026-04-17 air
Mali #8 Q3 2026 2026-05-05 2026-06-01 274,176 1,096,704 2026-05-14 ocean
Mali #9 Q2 2026 2026-06-22 2026-12-01 726,048 2,904,192 ocean

Shipment Documentation

Completed In Progress Not Started N/A
  Mali #6 Q2 2026 Mali #7A Q2 2026 Mali #7B Q2 2026 Mali #8 Q3 2026 Mali #9 Q2 2026
1. Certificate of Donation Complete Complete Complete Complete Not Started
2. Preliminary Green Light Complete Complete Complete Complete Not Started
3. Import Permit Complete Complete Complete Complete Complete
4. Proforma Invoice Complete Complete Complete Complete Not Started
5. Commercial Invoice Complete Complete Complete Complete Not Started
6. Packing List Complete Complete Complete Complete Not Started
7. Certificate of Origin Complete Complete Complete Complete Not Started
8. Certificate of Analysis Complete Complete Complete Complete Not Started
9. PS Inspection Report N/A N/A N/A N/A Not Started
10. Draft Waybill Complete Complete Complete Complete Not Started
11. Duty Waiver Complete Complete Complete Complete Complete
12. Final Green Light Complete Complete Complete Complete Not Started
13. Transport Booking Complete Complete Complete Complete Not Started
14. Final Waybill Complete Complete Complete Complete Not Started
15. Letter of Authority N/A N/A N/A N/A Not Started
16. Confirmation of Receipt Not Started In Progress In Progress Not Started Not Started
Update Notes Order #6: The vessel is scheduled to arrive in Dakar, Senegal, on May 22, 2026. A transit time of approximately three weeks is estimated from Dakar to Bamako.

Last Updated 2026-05-22 14:19:21 UTC