Child Survival Program

Back to Shipment Tracking

Azithromycin for Child Survival Shipment Tracker

Nigeria

2026 Shipment Summary
2026 Total Planned Shipment 26,665,508
Shipped Year to Date 0
Remaining to be Shipped 26,665,508

Shipment Information

Shipment Planned Shipment Date Planned MDA Date POS (Bottles) # of Treatments Shipment Date Arrival Date Mode
Nigeria #10 Q1 2025 2026-01-10 1,000,020 4,000,080 ocean
Nigeria #11 Q2 2026 2026-02-22 2026-06-01 1,200,000 4,800,000 ocean
Nigeria #12 Q2 2026 2026-02-01 2026-06-01 1,200,000 4,800,000 ocean
Nigeria #13 Q2 2026 2026-03-01 2026-07-01 777,216 3,108,864 ocean
Nigeria #9A Q4 2025 2025-12-19 2026-01-15 502,992 2,011,968 air
Nigeria #9B Q1 2026 2026-01-23 2026-02-01 549,216 2,196,864 air
Nigeria #9C Q1 2026 2026-01-01 1,436,933 5,747,732 air

Shipment Documentation

Completed In Progress Not Started N/A
  Nigeria #10 Q1 2025 Nigeria #11 Q2 2026 Nigeria #12 Q2 2026 Nigeria #13 Q2 2026 Nigeria #9A Q4 2025 Nigeria #9B Q1 2026 Nigeria #9C Q1 2026
1. Certificate of Donation Not Started Not Started Not Started Not Started Not Started Not Started Not Started
2. Preliminary Green Light Not Started Not Started Not Started Not Started Not Started Not Started Not Started
3. Import Permit Not Started Not Started Not Started Not Started Not Started Not Started Not Started
4. Proforma Invoice Not Started Not Started Not Started Not Started Not Started Not Started Not Started
5. Commercial Invoice Not Started Not Started Not Started Not Started Not Started Not Started Not Started
6. Packing List Not Started Not Started Not Started Not Started Not Started Not Started Not Started
7. Certificate of Origin Not Started Not Started Not Started Not Started Not Started Not Started Not Started
8. Certificate of Analysis Not Started Not Started Not Started Not Started Not Started Not Started Not Started
9. PS Inspection Report Not Started Not Started Not Started Not Started Not Started Not Started Not Started
10. Draft Waybill Not Started Not Started Not Started Not Started Not Started Not Started Not Started
11. Duty Waiver Not Started Not Started Not Started Not Started Not Started Not Started Not Started
12. Final Green Light Not Started Not Started Not Started Not Started Not Started Not Started Not Started
13. Transport Booking Not Started Not Started Not Started Not Started Not Started Not Started Not Started
14. Final Waybill Not Started Not Started Not Started Not Started Not Started Not Started Not Started
15. Letter of Authority Not Started Not Started Not Started Not Started Not Started Not Started Not Started
16. Confirmation of Receipt Not Started Not Started Not Started Not Started Not Started Not Started Not Started
Update Notes

Last Updated 2025-11-20 21:03:54 UTC